BIM promotes circularity

30 augustus 2021 door Diana Grasso

BIM2 met logo.jpg

The contractor used digital building models for ‘t Centrum, or BIM. This Building Information Modelling system is not a just a 3D model, it has several benefits. More accurate drawings, keeping an overview, and more efficiency during implementation are just a few of the benefits. Contractor Joeri Beneens explains what this means.

What is BIM?                                                                                                              

Joeri: “BIM is an acronym for Building Information Modelling. In recent years, construction projects are increasingly employing 3D models whereas they tended to rely on 2D drawings in Autocad and even pen and paper in the past. The step from 2D to 3D definitely was an improvement. With BIM, the drawing consists of more than just lines because we are able to add materials and information to the model. We create families or libraries in Revit, that we can use to design the building. We draw everything in 3D, starting from the foundation, working our way up to the structure, the walls, the windows in them. But there’s more: we are also able to model the building’s MEP systems. All the pipelines, HVAC (Heating, Ventilation and Airconditioning), the electricity, the BES field, the heat pump... We incorporate all of these systems to detect clashes at an early stage. This means we can resolve any conflicts in the design stage before building commences. We can thus exclude a large number of errors in the models, ensuring that we do not encounter them at the construction stage. We can thus work more efficiently and don’t have to deal with on-site errors that can be turn out to be quite costly. The 3D models take a lot longer to prepare compared with traditional 2D designs, but we make up for time lost by not having to deal with on-site errors.”

Urban mining

Does BIM provide (circular) added value and if yes, why?

Joeri: “What we have done today on this project is facilitate urban mining thanks to our BIM. This means that we can build future buildings with the material of buildings that we can no longer use instead of mining virgin materials for this. This is achieved by connecting the drawings with the building and making them sufficiently detailed and expanding them. Each part of the building is assigned its own number that is applied to the part itself, for example the foundation. These numbers are also used in the model. But this also works the other way around: if we dismantle the building, for example, we can tell where a specific part of the building used to be. If we have to demolish the building at some point, we can extract a list from the model in advance, which gives us an idea of how many foundations, beams, number of square meters of glazing, roof, insulation, etc. the building has. We append all the parameters of parts and materials that we need to know about to the model. The technical data sheets and how materials and structures are mounted and dismantled are also included in the model. This makes it easy to determine the value at the building’s end-of-life.”

How exactly did you incorporate BIM in this project? How much detail did you model?

Joeri: “West Architectuur started to work in BIM from the design stage onwards, which is why we have information about which systems are integrated in the building, down to the smallest details. So HVAC, parts of the HVAC, all the ventilation pipes, all the cable ducts and lighting, the climate beams... The Level of Development is between 400 and 500. This is an industry standard that defines how the 3D geometry of the building model can achieve different levels of refinement and is used as a measure of the service level required.”

Does Beneens use BIM on all of its projects? Do you see any major obstacles for incorporating BIM on all construction projects?

Joeri: “We currently use BIM on all of our timber construction projects. We will probably expand its use to more conventional construction projects in the long run. That is why we are currently looking to hire additional BIM draughtsmen who can work on our conventional projects. We have noticed that real estate developers are increasingly interested in incorporating BIM in projects.”

Has Beneens experienced the advantages of BIM first-hand since the integration? Have you noticed fewer issues/clashes on-site now that you use a BIM model?

Joeri: “We experienced the benefits of working with BIM since the first project that we developed in BIM. To be honest, I'm not sure how we would manage without BIM at this point. The Level of Development has only increased because we control machines. BIM will become more important, I think it will even become the standard at all companies. More architects will use it in their designs and supply BIM plans to contractors.”

Will the BIM model of ‘t Centrum be used at each stage (design, build, maintain) and if yes, how will it be used?

Joeri: “Yes, we used the BIM model at each stage: in the preparation, the implementation, production, execution, the installation of the building systems and in the post-intervention file. We will also append it to Calculus, a highly developed and detailed building management system. It will thus also be used to instruct the technicians that are in charge of the building’s maintenance. Reports will be generated, for example to replace the filter of the air group. The technicians will use the BIM model to determine on which floor and air group they must work. BIM helps them to visualise the situation.”

How do you collaborate with the other construction partners to develop one correct model? How do you exchange information?

Joeri: “Our construction company and the BIM manager play a coordinating role. He will request the details and diameters in advance from subcontractors such as Alucon, Benetech and Imtech. The cooperation is very efficient. We have also mapped these details for ‘t Centrum. All the pipes and cables have been added to the model. Obviously getting everyone to submit their drawing on time is always a challenge. And there are multiple choices to be made, in terms of lighting for example. Finding the most circular lighting proved more difficult than we thought. Once you have found  it, it needs to be added to the model. Deadlines are necessary for timely delivery to ensure that construction can move ahead as planned. In terms of exchanging information, everyone essentially works on the same file, which is stored on a drive and continually updated. All changes are confirmed by email.”

Further information about BIM: www.beneens.be

Photo: Dalux Viewer uses AR to visualise the building systems on the construction site of ‘t Centrum as part of BIM.

Labels:

  • The most circular office building of the Low Countries can be found at Kamp C in Belgium

    Kamp C, the living lab of the Province of Antwerp for sustainability and innovation in the construction industry, and a previously selected consortium of seven companies have recently completed ‘t Centrum in Westerlo (Belgium). This is the first completely circular office building in Flanders. The three-storey building has a total surface area of 2,400 m2. The building’s high level of circularity is remarkable. It has been entirely constructed from reusable materials and can thus be completely disassembled and rebuilt elsewhere. The builders used innovative materials, applications, techniques and new business models throughout.

    Lees meer
  • Calculus builds innovative management platform for ‘t Centrum

    ‘t Centrum uses innovative building management system Calculus developed a flexible, circular and remountable management platform for the circular office building to monitor and reduce water and energy consumption.

    Lees meer
  • Sheltered workshop Kunnig repurposes wood of Hangar 26 for use as façade cladding at ‘t Centrum

    Antwerp-based sheltered workshop Kunnig has prepared the façade cladding of former events venue Hangar 26 for reuse as façade cladding at ‘t Centrum. Kunnig gave the wood a total makeover. The wooden beams have now been given a new lease on life as façade cladding for ‘t Centrum, the circular office building at Kamp C.

    Lees meer
  • The challenges of a circular assessment process

    Streng-th, a structural engineering consultancy, was in charge of the analyses and assessments for circular office building ’t Centrum. This process proved quite challenging and in many respects it also different from a conventional project. Engineers Brecht Beirinckx and Stefan Belmans explain why.

    Lees meer
  • Magnesium oxide insulated panels for ‘t Centrum

    The walls of ‘t Centrum are clad with vapour-permeable, magnesium oxide insulated panels. Magnesium oxide has several circular properties and is fire-resistant. Bart D’Haese, an expert in Healthy Houses at EXIE NV, and contractor Joeri Beneens explain the reasons behind this choice. 

    Lees meer
  • Cellular glass for the circular roof of ‘t Centrum

    Cellular glass insulation was chosen for the roof terrace of 't Centrum, a circular office building in Westerlo (Belgium). The office building has been built in such a way that it can be dismantled and rebuilt elsewhere using the existing materials. The choice of cellular glass insulation, a material that is produced by FOAMGLAS ®, was made based on compressive strength to bear the load of the decking. Below we list four reasons why cellular glass is a good choice for a circular roof.

    Lees meer
  • How green walls make a difference in ‘t Centrum

    ‘t Centrum will have green walls throughout. But why do green walls make such a difference? And how do they influence circularity?

    Lees meer
  • 5 interesting facts about the vacuum glazing that is used in ’t Centrum

    Part of the glazing of ‘t Centrum consists of vacuum insulating glazing. Equal to triple glazing when it comes to performance, it has the slim profile of single glazing, however. We spoke with Stefan Lips, Sales Director at FINEO Europe.

    Lees meer
  • Cementless screed in ‘t Centrum

    Cementless screed was used in 't Centrum. This is a new circular screed. The screed consists of reclaimed sand from construction and demolition waste, street sand and sand from sewers. Wouter Cementless screed was used throughout ‘t Centrum. This is a new circular screed, made from reclaimed Vermin, Manager Treatment & Valorisation at Bioterra, explains what this means.

    Lees meer
  • Cellulose keeps ‘t Centrum warm

    Cellulose is the main insulating material that was used for the façades of ’t Centrum. This type of insulation is made from old, recycled newspapers. Why did the construction team opt for this insulation and what are the advantages? We discuss this in more detail in this article.

    Lees meer